These are the notes I had from the first production meeting (1st November):

·      Rehearsals: Goat and Tricycle 1 week, Winton Boys Brigade 2 weeks and University 1 week.
·      Stand in furniture for rehearsing.
·      All the doors swing both ways, cladding, double skinned.
·      Doors swing upstage.
·      Cash Register is part of the set rather than the props.
·      Windows, garden hinge back.
·      Goat and Tricycle 10am 12th November, design presentations.
These are my notes from the production meeting today:
Screen needs decoration both sides. What kind of fabric is this? Use the one they are using for rehearsals.
Lights on the tables (tea lights) and menu.
8 chairs, do we have these in props store, designer has to approve.
Cover the counter with fabric. The director doesn't want it to be silver on top.
Constructing Monday/Tuesday (week beginning 26th) Painting Wednesday till Friday.
Can we get the tables out of the doors, use the tables they rehearsed with-measurements.
Finish of the floor changed. Painting finishes at the interior then it goes to cobble stones and then fades to black. Planks for floor, might look like a sauna?
Monday morning mark out the set in the Winton Boys Brigade.
8 chairs wooden with no arms. Bentwoods, cafe style.
Tea lights and birthday candles needed.
Rehearsal Notes:
From p126. Miss Blumenblatt's.
Kitchen mid stage right.
2 separate flowers needed in vase, handed out.
Stage left upstage, table with 4 chairs. Wicker chair stage right.